Front door survey has been booked in for tomorrow and should be installed a fortnight after.
The roof beams are starting to go up, unfortunately the roof goes up a lot slower than the walls. The side extension will have a pitched tiled roof . There will be two flat roof windows here for the downstairs study /3rd bedroom and bathroom.
The rear extension will be flat roof with a roof lantern over the dining area.
The roof should be completed by the end of next week.
Inside the upstairs bathroom floor has been tiled, underfloor heating installed and the shower tray and toilet installed. The second fix for the bedroom has gone in with all spot lights and mains plugs installed.
I have ordered fitted wardrobes which will be installed in the last week of July.
I have decided to start on the rear garden. Due to the garden being on a slope we need to excavate soil to make a flat patio area and a retaining wall. The patio was going to be done at a later stage but as we are losing the side entrance due to the extension I don't want to remove 20 tonnes of soil through the house, so have bought this forward.